Indah Setiawati, The Jakarta Post, Jakarta | Wed, 02/17/2010 5:29 PM
Residents near East Flood Canal in East Jakarta have been enjoying a free-flood neighborhood after the operation by the government of the almost-finish canal since end of last year.
Cipinang Muara resident Hadiyati, 40, whose house is located around 20 meters from the canal, said that she and her family experienced no flood this year thanks to the newly constructed canal.
“In previous years, we would have had water level of up to two meters in height inundating our homes during the rainy season,” she said on Wednesday as quoted by tempointeraktif.com.
Antara News, Bustanuddin, Saturday, January 9, 2010 21:31 WIB
Jakarta (ANTARA News) - Only several days after welcoming the new year 2010, people in many regions, especially in flood- prone areas, have become depressed by the misery they have to suffer again from massive floods.
In Riau province, for instance, floods have inundated at least 13,236 houses in four districts after local rivers overflowed as a consequence of incessant heavy rains over the past few days.
The floods invaded among others 5,661 homes in Indragiri Hulu, 3,552 in Pelalawan, 2,950 in Kampar, and 1,050 in Rokan Hulu districts.
"As many as 56 villages in nine subdistricts in Indragiri Hulu district were the worst hit as the flood waters there reached heights of up to two meters," Head of the Riau Social Affairs Agency Raja Lukman Mat said recently, adding that his office had sent assistance to a number of flood-affected areas.
The relief assistance comprised foodstuffs and drinking water as well as rice, instant noodle, canned food, kerosene and emergency tents for the flood victims.
In addition, Coordinating Minister for People`s Welfare, Agung Laksono extended Rp1 billion worth of assistance for flood victims in Riau province on Friday (Jan 8).
Laksono symbolically handed over the assistance to Riau Governor Rusli Zainal at the opening of the Orphanage Jamboree in Pekanbaru, Riau, on Friday.
The minister requested that local government heads make an evaluation of the situation and find solutions to the reccurring floods.
"Regional governments should ask themselves why the floods happen again and again," he said, adding that the floods were very burdensome for the people, especially for those who every year are affected by the floods.
Apart from that, floods inundated around 2,089 houses in Tebo District, Jambi province, on Thursday following incessant rains during the past week. "Tabir sub district was the worst hit by the flood," RM Ali, head of the Tebo manpower and transmigration office, said here on Thursday.
Some 50 hectares of farming area were also submerged by the flood waters. In Tabir sub district, five villages were affected by the floods. In Embacang Gedang village, some 358 houses were inundated, in Pintas Tuo village around 388 houses, in Bangko Pintas village 87 houses and in Tanah Garo village 890 houses.
"According to latest data, some 1,723 houses in five villages have been affected," Ali said.In Serai Serumpun sub district, some 150 houses were flooded, and in Pagar Puding Lama village, around 50 hectares of farming area were inundated.
The flood waters also hit several other villages along the Batanghari river banks like those in Muara Tabir and Tebo Ulu subdistricts.
"The surface of Batanghari river had already risen in the past three days," said Samsir, a Puntikalo villager when asked in Muaratebo, capital of Tebo regency. He said hundreds of villagers sought higher grounds where the flood water cannot reach.
Samsir said that besides houses, three school buildings were also hit by the flood waters, and had to be closed. The schools included MIS Negeri Punti Kalo, SD 105 in Lebak Bungur village and MIS in Teluk Singkawan.
In addition, at least 30 houses and 20 fish ponds were inundated by a flash flood at Cilaban Bulan village, Menes sub district, Pandeglang District, Banten Province, on Wednesday.
"The flash flood did not claim any life as local residents were quick in evacuating themselves to safer areas," Ade Supriyadi, Cilaban Bulan village head, Menes sub district, said.
Heavy rain that had been falling in the village since 04 am local time and caused the Cilampuyang and Cigarugak rivers to overflow, he said. The flood waters reaching a height of up to 1.3 meter submerged 30 houses and 20 fish ponds.
Floods triggered by days of heavy rains inundated hundreds of homes at Jati Wetan village in Kudus district, Central Java, on Friday.
"The number of flooded homes at Jati Wetan village is about 500. The height of the flood waters varies between 40 cm and 50 cm," a local resident, Yusuf said.
In the meantime, Climatology Meteorology and Geophysics (BMKG) predicted that weather in Bogor district, West Java province in January was classified as normal.
"While in mid and late of January rainfall is high enough," Alidia of the BMKG told Antara on Thursday.Alidia said further that such condition caused by the low air humidity in Asia, while in the Australian region is high.
In the meantime on Wednesday, Vice President Boediono observed Jakarta`s East Flood Canal from a helicopter to obtain a personal impression of the progress achieved in the ongoing project.
During the aerial inspection, the vice president was accompanied by Jakarta Governor Fauzi Bowo and the head of the Ciliwung-Cisadane River Basins Authority, Pitoyo Soebandrio.
Public Works Minister Joko Kirmanto told the press at the vice presidential palace, work on the East Flood Canal which was intended to alleviate flooding in North and East Jakarta, had reached the Jakarta Bay coastline on December 31, 2009.
"The point is that when it rains, the East Flood Canal is already functioning, although not yet 100 percent," the minister said. According to Pitoyo Soebandrio, the East Flood Canal project was now 97 percent completed.
"As it is, the contractors will continue to work until June 2010. So, the worst possibility is that the East Flood Canal will be finished in June. But it could also be finished in March," he said.
When fully operational, the East Flood Canal will prevent flooding in at least 13 neighborhoods in North and East Jakarta, he said.
The 23-km-long canal cuts through seven river flows, namely the Cipinang, Sunter, Buaran, Cakung, and Jati Kramat rivers. The East Flood Canal project is part of an ambitious flood control master plan for Jakarta that was drawn up in 1973. The project was postponed many times due to lack of funding, land procurement problems and other obstacles.
Between 2001 and 2003, the city administration finally resumed the Rp 4.9 trillion ($519 million) East Flood Canal project. Jakarta suffers from annual flooding. In 2003 and 2007, the floods had disastrous consquences as they killed dozens of people
The canal is designed to contain 390 cubic meters of water per second, enough to avert flooding for at least 100 years in previously flood-prone areas.
Indah Setiawati, The Jakarta Post, Jakarta | Tue, 12/29/2009 8:29 PM
Governor Fauzi Bowo on Tuesday announced the East Flood Canal (BKT) would reach the sea on Dec. 31.
“As we have promised, on Dec. 31, the BKT will connect with the sea. But we have to admit that there are certain spots that haven't reached the required width,” he said on Tuesday.
Head of the Ciliwung-Cisadane Flood Bureau at the Public Works Ministry, Pitoyo Subandrio, confirmed the information, saying the width at some parts of the canal was still 15 meters from the required 70 meters width.
He said the areas needing widening were at the Kali Sunter bridge in East Jakarta, Pahlawan Revolusi bridge, ex-the power substation, Pondok Kopi, Haji Miran, Rawa Bebek and Marunda in North Jakarta.
The unfinished areas, he said, would not hinder the flow of water to the sea as the depth of the locations had reached four to seven meters.
“We have pushed the contractors to connect the canal to the sea by the end of December to mitigate the annual flood in January,” Pitoyo said.
He said the construction of the East Flood Canal was 96.5 percent complete, with the inspection roads, bridges and wire fence as the remaining projects.
He believed the contractors would finish the rest of the project before their contract term finished in June because the city had settled the hardest part – the land procurement – on Dec. 18.
Triwik Kurniasari, THE JAKARTA POST, JAKARTA | Tue, 03/03/2009 1:29 PM
Councilors have slammed the public works agency for not making the most of the 2008 budget to complete land acquisition for the East Flood Canal (BKT) project.
On Monday the agency reported it had only spent 30 percent of its budget in 2008.
Agency head Budi Widiantoro said his office had only used Rp 99 billion (US$8 million) of its Rp 300 billion municipal budget for last year’s BKT project.
“We also received about Rp 400 billion from the national budget, but the absorption was only about Rp 202 billion,” Budi said at City Hall.
“We faced some hurdles in the land acquisition process. For instance, we received the budget a bit late, in March.
“There was also a change in regulation. The National Land Agency [BPN] stipulated that there should be an appraisal process for all areas measuring more than one hectare.”
He added his office would appoint a consultant to conduct appraisals to speed the land acquisition process.
The administration has pledged to intensify land procurement in the near future for the canal.
The canal is aimed at reducing floods in a 270-square-kilometer flood-prone area straddling East and North Jakarta.
The agency also used up only 47 percent of its overall budget, far from last year’s budget absorption target maximum of 85 percent.
For 2009, the administration set the budget absorption at 95 percent.
Sayogo Hendrosubroto, chairman of City Council Commission D for development affairs, urged the agency to immediately complete the land acquisition.
“We approved a big portion of the budget for the canal project, but so far we have not seen the results. The agency has really failed to meet its budget absorption,” he chided.
“So we believe it doesn’t need a lot of money to complete the project. The budget will be useless.
“It would be better if they allocate a portion of the budget to improve the city’s public facilities, like fixing damaged roads and dredging rivers.”
Commission D member Irman Syukur agreed.
“We had high hopes that the administration would soon complete the acquisition process,” he said.
“The canal is important, but the agency should also pay attention to other facilities, like damaged roads across the capital. Many Jakartans have suffered a lot from the damaged roads.”
Agency data shows a total of 178.4 hectares of land in East Jakarta is needed to accommodate the canal and another 82.5 hectares for corridors beside the canal.
In North Jakarta, 78.6 hectares is needed for the canal, with 69.4 hectares for its corridors.
This year, Rp 250 billion is allocated for land acquisition in East and North Jakarta for the project.
Budi said his agency would allocate Rp 100 billion to procure land until March.
“We spent Rp 50 billion during January and February this year. We will allocate another Rp 41 billion this week,” he said.